Customer: PT Mitra Kiara

Place: Jakarta, Indonesia

Scope: Complete mixing plant for dry mortar incl. processing of limestone

Completion: March 2021

The latest major project is a dry mortar plant in Indonesia. In addition to the mixing tower with 2 mixing lines, the plant also includes the processing of natural sand and limestone with an edge length of up to 100mm for the mixing plant.

As part of the project, AML undertook the complete planning of the system, dimensioning and design of the machine technology, delivery of the machines and control system as well as the control assembly. Commissioning was completed  at the end of the first quarter of 2021 despite the global corona crisis.