Skip to content

Aramil

Aramil

Customer: OOO Kreps development

Place: Aramil, Russia

Scope: Complete dry mortar plant with sand processing

Completion: August 2014

In close cooperation with the customer, AML Anlagentechnik GmbH & Co.KG fulfilled all additional constructional and procedural related requirements which exceeded the ordinary mixing tower design. The result is a highly flexible production plant for a vast variety of products. After a short extension period the plant could double its output.

Alongside the basic engineering AML also handled the detail engineering for the electrical cable routes, the pneumatic conveying lines, compressed air pipes and the complete project work in the national language.

You can find out more about this project in our plant report published in the ZKG international magazine.